Beginning on Tuesday, October 6th, the City of Watertown’s asphalt paving contractor, Wolf Paving Co., will begin mill and overlay operations on E. Main Street between N. Tenth Street and S. Concord Avenue.

The Mill and Overlay of E. Main Street is part of the City of Watertown’s 2026 Street Resurfacing Program. The scope of work is scheduled as follows (dates are weather dependent).

  • October 6th – Pavement Maintenance, Inc. will mill the existing asphalt surface parking lanes.

  • October 7th – Wolf Paving Co. will pave a thin leveling course of asphalt over the existing asphaltic pavement. Wolf Paving Co. will then pave a new surface course of asphalt pavement.

Traffic Information During Milling Operations:

  • During the milling operations, traffic will be allowed through the construction via flaggers.

  • The contractor will sign “lane shifts” moving traffic away from the milling equipment.

Traffic Information During Paving Operations:

  • During paving operations, traffic will be detoured onto College Avenue, Western Avenue, and S. Concord Avenue.

  • Residents and businesses having properties within the construction zone will have access to their property during paving operations with some limitations.

The City of Watertown urges motorists to “Give ‘em a Brake” by slowing down and driving with extra caution through and near the construction zone. We appreciate your cooperation and understanding as we work to improve our City’s infrastructure.

Questions can be directed to the City of Watertown Engineering Department at (920) 262-4060 Motorists are encouraged to use caution when traveling near and through the work zone and consider alternate routes when possible. The City appreciates your patience and cooperation in this matter.