Main Street Construction Plan
We know there is a lot going on downtown, and while the plans can change (because most are projects involving the Wisconsin Department of Transportation), here is the plan for Main Street infrastructure:
2022 – late summer/early fall:
- Mill and overlay driving lanes
- Seal coat parking lanes
- New pavement marking
2025:
- Main Street (Cole) Bridge replacement (may move up to 2024 if state funding is available)
2028:
- Full roadway reconstruction from Church Street to Market Street
- Water main, storm sewer replacement
- Pavement, curb and gutter, and sidewalk construction
2029:
- Full roadway reconstruction from Market Street to Irene Street
- Water main, storm sewer replacement
- Pavement, curb and gutter, and sidewalk construction